The forward pass in project network calculations determines all of the following except


MC Qu. 18 The forward pass in project network... 15 The forward pass in project network calculations determines all of the following EXCEPT olnts Multiple Choice Print Duration of the project References Earliest time an activity can begin. The critical path. Earliest time an activity can finish. How soon the project can finish.

Answer

Ques- (c) The forward pass in project network calculations determinies all of the following except the critical path.

The forward pass in project network calculations determines Early start, Early finish, and the Duration of the project.